GOGC Is Constructing 12,5 km section of Kobuleti Branch of the East West Main Gas Pipeline
09 September, 2019
Georgian Oil and Gas Corporation (GOGC) is constructing 12,5 km section of Kobuleti DN 500 60 km branch of the East West Main Gas pipeline.
At this stage, productive layer of the soil has already been removed and pipeline welding has commenced.
The works are being performed by the tender winning Turkish company “Ozsoy Muhendislik Ticaret A.S.”
Last year GOGC constructed 45 section of the 60 km Kobuleti branch of the East West main gas pipeline.
The cost of the (12.5 km section) construction project is GEL 4.555.979-99.
The completion of the DN 500 60 km section of Kobuleti branch of the East West Main Gas pipeline will ensure meeting the increased demand for natural gas in the Ajara region.
At this stage, productive layer of the soil has already been removed and pipeline welding has commenced.
The works are being performed by the tender winning Turkish company “Ozsoy Muhendislik Ticaret A.S.”
Last year GOGC constructed 45 section of the 60 km Kobuleti branch of the East West main gas pipeline.
The cost of the (12.5 km section) construction project is GEL 4.555.979-99.
The completion of the DN 500 60 km section of Kobuleti branch of the East West Main Gas pipeline will ensure meeting the increased demand for natural gas in the Ajara region.