February 22, 2018 Georgian Oil and Gas Corporation is Constructing Gori-Kareli-Khashuri 17 km Section of the East-West Main Gas Pipeline

Georgian Oil and Gas Corporation (GOGC) is constructing a new DN 700 Ptsa-Chorchana 17 km segment of Gori-Kareli-Khashuri section of the East-West Main Gas Pipeline.  

February 8, 2018 Adjara and Guria regions are not under threat of termination of gas supply

The Georgian Oil and Gas Corporation relocated 700 m section of Kutaisi-Sukhumi main gas pipeline Kobuleti branch to the new corridor, eliminating the threat of termination of gas supply to two regions.

January 22, 2018 Akhalkalaki region will receive natural gas at high pressure

Akhalkalaki region will receive natural gas at high pressure. This will be allowed by the works performed by GOGC on the 6 km section of the high pressure gas pipeline.